A6 Randalstown - Castledawson Dualling Scheme

Delivered by the Department for Infrastructure the A6 Dualling Scheme will upgrade 14.7 kilometres of  Transport Corridor between Randalstown and Castledawson, a route used by 20,000 vehicles each day, which often experiences congestion at key times.

Graham Farrans Joint Venture have been awarded the contract of this essential work, which once completed, will bring long term social and economic benefits to the local area.

The flagship investment of £185m will strengthen the links between Belfast and Derry/ Londonderry and will bring the long term benefits to road users and the local community of reduced journey times and improved road safety.

Work is being carried out on an area based construction programme and is expected to be completed by 2021.

Alerts & Updates

  • The B183 Moneynick Road will be temporarily closed at the Drumderg Roundabout approach from 10pm Friday 6 September - 6am Monday 9 September 2019
    Local access will be maintained to Moneynick Road via Randaslstown slip road, which will be opened in both directions
  • A6 Randalstown - Toome, including M22 junction 3 fully open to live traffic
    Thank you to all residents and travelling public for your patience and support during construction works.
  • Derrygowan Road reopens to Live Traffic
    Thank you to all local residents for your patience and support during the construction

Report an issue

Please use the form below to report any issues or contact the 24 hour phone line on 02890394090

Report an issue

The Team


Principal Contractor
Client
Design Consultants
Client Representative