Significant progress is being made on the A6 Dualling Scheme with final surfacing works underway and some upcoming openings ....

The Graham Farrans Joint Venture continue momentum with the works on the A6 Dualling Scheme with further  Temporary Traffic Management planned for July to help the works progress.

 

Randalstown off-slip 

ROAD CLOSURE  - RANDALSTOWN OFF-SLIP

The Randalstown Off-Slip at the M22 will be temporarily closed to traffic from 1 July 2018 - 2 September 2018 to allow the construction of a new grade separated Junction 

  • Diversion route via M22 Eastbound to M22 Junction 2 *non-motorway traffic permitted to travel to M22 Junction 2 during closure 

 

Bellshill Road Temporary Closure 

TEMPORARY ROAD CLOSURE  - BELLSHILL ROAD (S) 

The Bellshill Road (S) will be closed for a period of 2 weeks from Monday 25 June  2018 - 9 July 2018 to facilitate the continuation of earthworks and drainage in the area.

  • Local access will be maintained via the Aughrim Road 

 

Gallagh Road Permanent Closure 

PERMANENT ROAD CLOSURE - GALLAGH ROAD 

The Gallagh Road will be permanently closed from 16 July 2018 

 

Ballynafey Road and Ranaghan Road Opening 

ROAD and BRIDGE  OPENING  - BALLYNAFEY / RANAGHAN ROAD 

The Ballynafey and Ranaghan Roads will be reopened from Monday 16 July 2018 

 

 

Derrygowan Road Temporary Closure

TEMPORARY ROAD CLOSURE  - DERRYGOWAN ROAD 

The Derrygowan Road will be closed from 16 July 2018 for approximately 1 year

  • Local access will be maintained via Staffordstown Road 
  • Alternative access to Woodcraft Joinery has been created on the A6 Mainline 

 

Annaghmore Rd (S) Temporary Road Closure and Night Works 

ROAD CLOSURE  - ANNAGHMORE ROAD (S)

The Annaghmore Road will be closed to traffic on 7 August 2018 from 10pm - 6am to facilitate NIW connection works 

  • Local access will be maintained via Aughrim Road 

 

Annaghmore Road Temporary Traffic Lights

TEMPORARY TRAFFIC LIGHTS  - ANNAGHMORE ROAD (S) 

The Annaghmore Road (S) will be have temporary traffic lights operating for a period of 2 weeks from Monday 23 July  2018 - Tuesday 7 August 2018 to facilitate NIW Connection Works.

 

Ongoing Temporary Closures ...

A6 Mainline will be closed between J2 M22 - Drumderg Roundabout from 3pm - 3.30pm to facilitate blasting works in Borrow Pit P on; 

  • Saturday 28 July 2018 
  • Saturday 11 August 2018
  • Saturday 25 August 2018

 

Opening of new Toome Park and Ride Facility 

 PARK AND RIDE OPENING